Six 21-ton excavators, from Qingdao to a construction site in Antioquia
- Industry
- Construction
- Route
- Qingdao → Cartagena → Medellín
- Equipment
- 6 × 40' flat rack
- The challenge
- The machines exceeded the container width and the site had a fixed start date.
- What we did
- Shipment on flat racks with a lashing plan approved by the carrier, early declaration and lowboy trailers with permits ready before arrival.
- The result
- All six machines left the port within the free days and reached the site in a single convoy.